III. WORK PROJECTS, CCC
100+
Miles of Fire Breaks
10
Miles Phone Line
8,000
Gallons Oil Used
25
Miles Trails Mowed
A
Lookout Tower
Painted with
three coats
(first two-thirds, then full coat)
Trap door fitted with balanced weight
Base cleaned and covered with hay to prevent blow-outs
One-room cabin relocated from "21" ranch for use by patrol/lookout staff
Small garage also relocated and rebuilt
B
Parking Areas and Overlooks
East-west roads at headquarters oiled with
8,000 gallons
using sand-clay mix
Created
5,000 cu. yards
of bituminous mat
Compacted by rolling; significant site improvement
C
Earth Excavations
10 potholes
dug near Watts Lake to create waterfowl habitat
Each approx.
80'×100'
,
3½–4½ ft
deep
All retained at least
1'
of water
D
Fire Breaks
100+ miles
reconstructed using International "40" tractor and rooter disc
Additional discing in vegetated areas
Fire breaks near
110-mile
boundary completed
Need for annual discing and suitable refuge equipment noted
E
Nurseries
Six
nursery plots weeded twice
Installed
200 GPM
turbine pump at Whitewater Lake nursery
Poisoned grasshoppers with arsenic mix – effective
Summary of seedling growth from Apr–May plantings (includes Green Ash, Chinese Elm, Black Locust, etc.)
F
Reconnaissance and Investigation
Vegetative range mapping in east refuge started – to be completed in September
G
Seed Collection
Hand-collected wild seeds:
Wild Currant –
7 lbs
Chokecherry –
600 lbs
Plums –
9 bushels
Crop yields lower due to dry weather
H
Preparation and Transportation of Materials
Cleanup of old WPA "21" ranch site
Salvaged material prepared for use in LaCreek Refuge
I
Wells
Three holes
drilled before water was found near 21 ranch grazing area
J
Fire Hazard Reduction
Double shifts mowed vegetation along trails
25 miles
of trails mowed (
12'
wide strips),
50 acres
cut and piled
Used hay for sandy road coverage
Smoking rules enforced; fire watch established in Hackberry tower
K
Telephone Line
10 miles
of line strung; phone installed in Hackberry fire tower
Not connected due to July 27 fire equipment loss and family illness of installer
L
General Cleanup
Cleared burned barn site; identified remains and reported losses
M
Fences
Reconstructed
2 miles
south of Mule Lake
Repaired
6 miles
of fencing north/west of Middle Marsh
N
Truck Trails
½ mile
near Duck Lake clayed and graded (test comparison)
Surveying road from Long/Duck lakes to West Hackberry Valley
Trails hayed to aid vehicle passage (
6 miles
near Pony Lake,
8 miles
in NW area)
O
Surveying in Connection with Other Work
Preparing comprehensive groundwater survey (to tie into U.S. Geodetic Survey)
Preliminary nursery and road alignment surveys done
Trails to be surfaced with magnesia clay and hay due to lack of gravel